In October 2021 we started designing this structure, in January 2022 we could start production. Together with Arcadis we could start working on the foundation and infrastructure. The first parts arrived the end of February, we started construction the mid of March, parts would arrive during construction.
Start construction:
March 15 2022
Completed :
April 30 2022
Client :
Floriade BV
During 6 weeks we constructed the second Floriade structure.
Especially the foundation was complex, since the Floriade will be dismantled in October 2022, every foundation must be removed, and using piles was no option.
The Floriade area is in Flevoland province near the city of Almere, it is the newest province and 60 years ago this area was still water, a solid layer can be found on 26m in depth. Together with Arcadis, we had to design a creative, temporary and affordable solution.
Our foundation is usually 2 x 2 m stelcon plates, easy to place and easy to remove. On these stelcons we place our connectors and build from there.